• All interior doors have been ordered but we have to wait about a month. Expected delivery is 9/14/05.
• The garage door was installed.
• Interior of house and garage has had two coats of primer applied.
• Master bathroom has been floated and is ready for tile.
• The ceiling beams are being installed single-handedly by Dave Barlow. The planning for this was extremely difficult as there is quite a bit of wood and detail in a Craftsman style house. We are designing the layouts on the fly for the ceiling, crown moulding, plate/picture rail, floor trim, wainscoting, and staircase. All of these pieces tie together as one entire wood 'system'. Our design of this is staying about one or two steps ahead of the build. One problem is that we don't have our wood floors in yet so we can't build the jambs up from the floor.