Cabinets, Plumbing, Electrical, Insulation, Surround Sound, Roof Work, Shower Mopped,.....

I have been really busy and haven't had time for updates. I have finally organized the new pictures since my last posting on 4/16/05. I will load them up sometime this week, I promise. Here are the latest issues.
• All plumbing and electrical in the master bathroom has to shift to the left by about a foot since we had a designer lay out the cabinets.
• All insulation has been put in.
• I installed in-ceiling speaker brackets for surround sound in the living room.

Ceiling Speaker Bracket Installed


• Copper flashing is going on the roof.

Copper Flashing Installed on Roof


• The shower has been hot-mopped. We were told to pick out all bathroom tile and balcony and laundry room flooring this week.

Hot Mopped Shower


• Skylights have been framed.

Framed Skylight


• The kitchen range vent has been put in place. One of the joists had to be moved over and plumbing rerouted to make room.
• The Thermador range and Thermador dishwasher were delivered last week. I found a place in Alabama (Fredrickson's Tire and Appliance) with amazing prices through eBay. They were clearing out a supply of Thermador appliances from a warehouse that closed down. They bought everything up and were liquidating at wholesale prices.
• With the extended garage roof you now hit your head when walking around the corner. So, we dug down about 2 feet around the garage to lower the grade.