I have finally uploaded the pictures for the last 2 months.
• Today I went to the neighbor over my backyard fence to inform her that a survey was done and the fence needs to move about 10 feet onto her side. She said do whatever I need to do. Now wasn't that nice? I told her I'll landscape her side of the fence.
• The roofer has started to cover the black paper with a rough asphalt paper.
• The front door jamb has been installed.
Visit the Craftsman Home Remodeling Website
Wednesday, June 15, 2005
Survey Says...Move the Fence!
Labels:
Bungalow,
Construction,
Craftsman,
Remodel,
Survey
Tuesday, June 14, 2005
Cabinets, Plumbing, Electrical, Insulation, Surround Sound, Roof Work, Shower Mopped,.....
I have been really busy and haven't had time for updates. I have finally organized the new pictures since my last posting on 4/16/05. I will load them up sometime this week, I promise. Here are the latest issues.
• All plumbing and electrical in the master bathroom has to shift to the left by about a foot since we had a designer lay out the cabinets.
• All insulation has been put in.
• I installed in-ceiling speaker brackets for surround sound in the living room.
• The Thermador range and Thermador dishwasher were delivered last week. I found a place in Alabama (Fredrickson's Tire and Appliance) with amazing prices through eBay. They were clearing out a supply of Thermador appliances from a warehouse that closed down. They bought everything up and were liquidating at wholesale prices.
• With the extended garage roof you now hit your head when walking around the corner. So, we dug down about 2 feet around the garage to lower the grade.
• All plumbing and electrical in the master bathroom has to shift to the left by about a foot since we had a designer lay out the cabinets.
• All insulation has been put in.
• I installed in-ceiling speaker brackets for surround sound in the living room.
• Copper flashing is going on the roof.
• The shower has been hot-mopped. We were told to pick out all bathroom tile and balcony and laundry room flooring this week.
• Skylights have been framed.
• The Thermador range and Thermador dishwasher were delivered last week. I found a place in Alabama (Fredrickson's Tire and Appliance) with amazing prices through eBay. They were clearing out a supply of Thermador appliances from a warehouse that closed down. They bought everything up and were liquidating at wholesale prices.
• With the extended garage roof you now hit your head when walking around the corner. So, we dug down about 2 feet around the garage to lower the grade.
Labels:
Bathroom,
Bungalow,
Cabinets,
Construction,
Craftsman,
ebony,
electrical,
Insulation,
mahogany,
Plumbing,
Remodel,
thermador