Saturday, April 16, 2005

First Window Installed

Today I helped install the first windows. They look even better than I hoped they would.

First Installed Loewen Window

Thursday, April 14, 2005

Windows and Doors Delivered

The Loewen windows and doors were delivered today. There is a scratch on the 8' french doors. Somebody will need to come out and fix that. I'm told it will be after all exterior work is complete.


Tuesday, April 12, 2005

Everyone is Working, Picking Fixtures, Designing Landscape, Where's My Garage

• The rough plumbing is going well. Only about 4 more days until it's done.
• The master bathroom shower, sink, and tub fixtures were picked today. They are made by Phylrich - Carrara Beige Model Series. The finish is oil rubbed bronze with the beige marble handles.
• Chose Mr. Steam MS-400T for the master bath steam shower. I purchased it and then found it for about $150 less. Oh well, maybe I'll save next time. This site has everything!

Mr. Steam MS 300T


• The electrician started today and mounted electrical boxes around the house. It seems the code of a box every 6 feet is excessive.
• The garage was torn down today due to wood rot and termites in preparation for the new garage framing and roof. This was not part of the original plan.

Garage Torn Down


• Hired John Bauman, landscape designer and former owner of the Begonia Farm Nursery.

Monday, April 4, 2005

Fireplace Construction Starts

Pete Ramage of Ramage Masonry has started the fireplaces and the plumber, Jaime, is putting in the gas lines to them.