It's raining again! The tarp on the roof started to blow off so Rich went onto the wet, shake roof with muddy shoes. Needless to say, he slid all the way off. He said he is just fine but probably used up one of his nine lives.
Visit the Craftsman Home Remodeling Website
Friday, January 28, 2005
Friday, January 21, 2005
Foundation Snag
Major issues today. The city building inspector came by and said that we can't build a second story on a foundation wall that is only 6" wide (six inches is standard for one-story houses here). So he decided to stop the concrete pour before we started. Rich had to run to the city engineer to have all of the calculations reverified per the city. That apparently was not good enough so luckily we got the engineer to come out to the house and visually inspect the footings. Everything was OK and we got to pour on Monday. That cost us a few days.
Tuesday, January 18, 2005
Windows and Doors Ordered
Loewen windows and doors were ordered today. They will be push-out, french casements in a cranberry color.
On a completely unrelated note, I was told that the concrete for the foundation under the house will be poured on Friday, 1/21/05.
On a completely unrelated note, I was told that the concrete for the foundation under the house will be poured on Friday, 1/21/05.
Monday, January 17, 2005
Timber Reused When Possible
Much of the large timber frames from the demolition were saved for reuse during the project. For example, several 2 x 6's were used to reinforce the floor joists. Rich Wright prides himself on being able to save the wood and reuse it whenever possible. Several very large beams from the living room will most likely be reused in the new living room.
Labels:
Construction,
Recycling,
Remodel,
Rich Wright,
Wood timbers
Saturday, January 15, 2005
Trying to Get Ideas in Pasadena
Today we drove around Pasadena to look at various color combinations on Craftsman and Bungalow houses. Click here to see them.
Friday, January 14, 2005
The Steel Beam is Installed
The 22 foot, 1,200 pound steel beam was put in place today and nobody got hurt. ;o)
This beam was put in to support the second floor balcony.
This beam was put in to support the second floor balcony.
Tuesday, January 11, 2005
Foundations and Rain
The first stretch of dry weather is finally here. The last 2 1/2 weeks have been nothing but rain, about 10 inches worth. The outside trenches have water in them but on the other hand, the demo guys are having a field day. There are now 10 guys working on the site. Five of them are under the house digging a massive trench for the foundation reinforcement. Things should happen quickly now.
Subscribe to:
Posts (Atom)